OXBOW ROAD WATERLINE REPLACEMENT

The project consists of removal and installation of approximately 1,100 feet of 6-inch Asbestos Cement (AC) and C900 PVC pipe, respectively, between F 3/10 Rd and F 1/2 Rd; including installation of fire hydrants, connection to existing mains and services, and other miscellaneous work as described in the Contract Documents.

PRE-BID MEETING 

  • Mandatory 
  • May 16, 2024
  • Intersection of Oxbow Rd and F 3/10 Road 

BID DATE

  • May 23, 2024
  • Ute Water - 2190 H ¼ Road
AddendumInvitation to BidBid ResultsPre-Bid Meeting NotesPre-Bid Meeting Attendees

Oxbow Road Project Details

10 ROAD WATERLINE REPLACEMENT

The project consists of installation of approximately 6,400 feet of 8-inch C900 PVC pipe, including installationof fire hydrants, connection to existing mains and services, and other miscellaneous work as described in the Contract Documents.

PRE-BID MEETING 

  • Mandatory 
  • March 28, 2024 
  • Intersection of 10 Road and Q 3/4 Road 

BID DATE

  • April 4, 2024
  • Ute Water - 2190 H ¼ Road
AddendumInvitation to BidBid ResultsPre-Bid Meeting NotesPre-Bid Meeting Attendees

10 Road Project Details

F 1/2 ROAD PARKWAY - PHASE 1

The project consists of installation of approximately 1,700 feet of 8-inch C900 PVC pipe, approximately 400 feet of 12-inch C900 PVC pipe and approximately 150 feet of 10-inch C900 PVC pipe, including installation of fire hydrants, connection to existing mains and services, and other miscellaneous work as described in the Contract Documents.

PRE-BID MEETING 

  • Mandatory 
  • July 13, 2023
  • Intersection of Market Street and F 1/2 Road

BID DATE

  • July 20, 2023
  • Ute Water - 2190 H ¼ Road
Bid ResultsInvitation to BidPre-Bid Meeting NotesPre-Bid Meeting Attendees

F 1/2 Road Project Details